Kostolac B3 lignite power plant, Serbia
Serbia’s state-owned utility Elektroprivreda Srbije is planning a new 350 MW lignite plant at Kostolac in the country’s north-east. In spite of high level support and Chinese financing, the project is plagued by concerns over pollution, State aid and legal challenges.

Stay informed
We closely follow international public finance and bring critical updates from the ground.
Background
Serbia relies on lignite for around 70 percent of its electricity production, which poses challenges in switching to a sustainable low-carbon economy in line with EU policy. It also poses problems in terms of climate change resilience, as the floods in 2014 showed (see below).
Nevertheless, the Serbian government and state-owned utility Elektroprivreda Srbije (EPS) plan to build more coal plants. Top of the list is Kostolac B3 near Pozarevac.
The construction of the 350 MW lignite power plant is the second phase of a project implemented by the China Machinery Engineering Corporation (CMEC) and financed by the China EximBank.
The first phase, for which a USD 293 million financing contract was signed between the Government of the Republic of Serbia and Chinese Exim Bank on 29 December 2011, consisted of modernization of the existing units Kostolac B1 and B2, construction of a desulphurization system, a landing dock on the Danube and railway infrastructure.
Would you trust these companies to build a new coal plant?
The Kostolac B3 chimney may be under construction, but EPS and CMEC are yet to get the desulphurisation unit working that CMEC built several years ago at the existing Kostolac B1 and B2 plant. The whole desulphurisation project has been marked by back-to-front processes, but is getting more mysterious as time goes on.
Construction was already underway in June 2015, before the environmental impact assessment (EIA) procedure for the desulphurisation unit was anywhere near concluded. The public debate on the EIA took place on August 18, when the unit was already half-built. The construction permit for the desulphurisation unit was issued on 31.8.2015, in record time after the public EIA debate.
On 18 July 2017, the Serbian Prime Minister announced the completion of Kostolac desulphurisation unit, yet as of January 2020, it is still not operating.
As a result, in 2018 Kostolac B’s emissions were the highest of any coal plant in the Western Balkans, and were 14 times above the plant’s allowed emissions ceiling.
The Serbian authorities have stated that the landfill needed to receive the gypsum waste from the desulphurisation unit is not ready. But does really take so long to dig a hole and line it?
To add to the mystery, in December 2019, the Serbian Ministry of Environmental Protection opened a public consultation on a new environmental impact assessment for the desulphurisation unit, despite it having been built for two and a half years already.
Whatever is going on, it does not inspire confidence in EPS and CMEC, nor in the Serbian government’s ability and willingness to enforce the law. Under these circumstances, surely it would be better to get the desulphurisation unit at the existing plant to work, rather than pushing on with the construction of a new plant?
In November 2013, the Serbian government signed an agreement with CMEC for the construction of the new unit, B3. No tender procedure took place. Instead, the Chinese and Serbian governments signed an intergovernmental agreement freeing joint projects from tender obligations – a move which would not be allowed under EU law.
A second, USD 608 million loan was signed between the Serbian government and the China EximBank in December 2014 for the new unit and expansion of the Drmno open cast lignite mine, whose annual production would increase from 9 to 12 million tonnes.
On 19 January 2015, the Serbian parliament voted on the loan ratification in an extraordinary session announced to the public less than 24 hours in advance. It includes several problematic elements, including stipulating that any arbitration would be carried out in Beijing.
As of January 2020, the project continues to accumulate legal challenges and other issues, but EPS seems determined to go ahead.
No environmental assessment for mine expansion
The Drmno mine currently produces around 9 million tonnes of lignite per year and needs to expand to 12 million in order to feed the new plant. In 2013 the government decided that no environmental impact assessment would be necessary for the mine expansion. This is currently subject to a complaint to the Energy Community Secretariat by Serbia’s Center for Ecology and Sustainable Development (CEKOR) and Bankwatch.
Successful court challenge and Espoo Convention complaint sent Environmental Impact Assessment back to the drawing board
The first environmental impact assessment for Kostolac B3 was approved in December 2013. It lacked any analysis of transboundary impacts, even though the site is just 15 km from the Romanian border, and suffered from numerous other deficiencies. It was therefore challenged in court by CEKOR and at the Espoo Convention by Bankwatch Romania.
At its 33rd meeting held in March 2015, the Espoo Convention Implementation Committee noted that the construction of a unit at the Kostolac lignite power plant was an activity listed in Appendix I to the Convention and that the likelihood of a significant adverse transboundary impact could not be excluded.
Therefore, the Committee asked Serbia to comply with its obligations under the Convention and to notify Romania about the environmental impact assessment. This was the first time that the Committee has opened an initiative related to cross-border impacts of a coal fired power plant.
In June 2016 the Serbian administrative court ruled that CEKOR’s arguments were valid and that the decision to approve the environmental assessment should be revoked. By this time, however, the original decision had already expired and the environmental assessment had to be started again.
A new environmental impact assessment process was carried out in 2017, also with transboundary consultations, and approved in September. However it still suffered from a number of weaknesses such as failure to ensure that the planned plant complies with current EU pollution standards, the so-called LCP BREF, and failure to address the concerns of residents of the village of Drmno regarding their health and property damage from vibrations and ground subsidence. Therefore CEKOR has again challenged the decision in court.
Mystery construction permit
Just weeks later after the environmental assessment was approved, on 20 November 2017 – and a few days before the China-Central & Eastern Europe summit in Budapest – it was suddenly announced that construction of Kostolac B3 was starting. Surprised, CEKOR requested the building permit. However the permit was for the B3 chimney only, not for the whole plant. And it is dated July 2017, before the environmental assessment was even completed.
In fact, the building permit for the main boiler and other key parts of the power plant were only issued in April 2019, when the chimney was already at an advanced stage of construction.
Risks from flooding
Such vulnerabilities have not been taken into account while planning the new unit.
A mining pit Kolubara, another lignite mine in Serbia, under water following the floods.
Read more When water mixes with coal – The impacts of the floods in Serbia on people living next to lignite mines Blog post | May 30, 2014 EBRD in Serbia: Don’t use floods to prop up coal Press release | July 7, 2014
Latest news
How Serbia’s addiction to coal could cloud its future in Europe
Bankwatch in the media | 21 November, 2020Source: How Serbia’s addiction to coal could cloud its future in Europe
Read moreTermoelektrana Kostolac A u „penziju“ ide tek 2038. godine
Bankwatch in the media | 22 October, 2020Source: Termoelektrana Kostolac A u „penziju“ ide tek 2038. godine
Read moreEPS plans to extend lifespan of TPP Kostolac A until 2038
Bankwatch in the media | 15 October, 2020Source: EPS plans to extend lifespan of TPP Kostolac A until 2038
Read moreRelated publications
Risks for coal and electricity investments in the Western Balkans, Ukraine and Moldova due to state-aid rules
Study | 8 June, 2015 | Download PDFBy signing the Energy Community Treaty in 2005, countries in the Western Balkans, Ukraine and Moldova agreed that the European Union’s competition rules are to be applied also within their territory. A number of energy sector investments are being planned that may not so far have taken adequate account of State aid rules. This briefing therefore provides a summary to draw attention to relevant requirements of EU law and highlight the risks of failure to take them into account when planning investments. The account when planning investments.
Where will all that power go? New study assesses extravagant energy ambitions in the western Balkans
Bankwatch Mail | 14 May, 2015 |Western Balkan countries have ambitious plans to increase their electricity generation over the next years. But what will happen if they all become a regional energy hub? Will there be a demand for all the available electricity?
Stranded assets in the Western Balkans – report on the long-term economic viability of new export capacities
Study | 19 March, 2015 | Download PDFCountry chapters available for Albania, Bosnia and Herzegovina, Kosovo, Macedonia, Montenegro, Serbia. For other languages, see here. Analysing the estimated energy demand and production capacities in Western Balkan countries, this study shows that if countries realise their planned capacity expansions, the region will have a 56 per cent electricity surplus in 2024, led by Bosnia and Herzegovina and Serbia. Nearly all governments in the region aspire to become electricity exporters, but the study argues that if governments fail to take into account the regional perspective, they could end up with power plants becoming simply uneconomic to operate.