Rovinari unit 7, Romania
CANCELLED: The Romanian Government has been negotiating for several years with the Chinese Government to build a new 600 MW unit at the lignite power plant in Rovinari, Gorj County. The new unit would be built on the site of Units 1 and 2, currently decommissioned. A new up and running plant would pollute the whole region for at least 40 more years, a coal plant’s average lifespan.

Stay informed
We closely follow international public finance and bring critical updates from the ground.
Background
In December 2012 Oltenia Energy Complex (state owned company) signed a memorandum of understanding with China Huadian Engineering Co. Ltd for setting up a project company and the construction of a 500 MW lignite-fired unit at Rovinari. The initial information was that the new unit would be built at an estimated cost of one billion euros. Since then, more memorandums of understanding have been signed between the Romanian and the Chinese company or the respective Governments, laying down the steps to create a Romanian-Chinese joint-venture, which would implement the project. The most recent one dates to September 2015, when it was reported that the unit would have an installed capacity of 600 MW and would cost EUR 847 million. The project team has met since them, the latest visit of a Chinese delegation to Rovinari taking place in August 2017.

In January 2013, the general manager of the Oltenia Energy Complex said the new unit will export the electricity to Austria and Turkey. China Huadian conducted a pre-feasibility study in 2014 for the construction of this unit at Rovinari, indicating the need to dismantle some of the existing infrastructure, something that would increase the costs of the project and which the representatives CE Oltenia disagreed with at the time. In addition, China Huadian Engineering Co. requested customs exemptions for equipment imported from China, demanding at the same time a long term power purchase agreement or a guaranteed price for coal, which, under European legislation, may be considered illegal state aid. China Huadian would ensure the full financing of the investment, being the main shareholder of the joint venture IPP (Independent Power Producer) that would be created and CE Oltenia would have a share of under 9%.
If the project went ahead, the new unit would be located next to the town of Rovinari, increasing existing air pollution levels from the other 4 units. The lignite would be supplied from the nearby open-pit mines – Tismana I and II, Rosia, Pinoasa, all owned by the same Oltenia Energy Complex – which would require expansion of production capacity. Extending these mines would mean clearing huge land areas, in most cases accompanied by massive deforestation.

Since 2012, Bankwatch Romania has filed a series of complaints in court, requesting the annulment of illegally issued deforestation permits and mine expansion permits which did not assess impacts on the environment. Almost all the actions have been successful in court. After an infringement procedure was initiated by the European Commission, all expansions were reassessed. However, the new permits fail to evaluate the cumulative impact of the mines, and are therefore again the subject of Bankwatch Romania court action, one of them being currently suspended. To date (May 2018) no environmental impact assessment procedure has been launched.
In short:
The existing power plant: – Part of Oltenia Energy Complex – 4 units installed every 330 MW each – Three functional units: 3, 4 and 6; unit 5 undergoing modernisation – Location: southwestern Romania, Gorj county – Year of commissioning: 1972 – Fuel used: lignite – Environmental integrated permit expired on 31.12.2017
New power plant – China Huadian + CEOltenia – 1 unit of 600 MW – Fuel: lignite (6 million tonnes per year) – Life expectancy: 40 years – Significant social and environmental impacts
Latest news
Bosnia and Herzegovina’s draft NECP: The good, the bad and the ugly
Blog entry | 20 July, 2023Bosnia and Herzegovina’s draft NECP finally looks to the future, plans no new fossil fuel power plants and significantly scales back unrealistic hydropower plans. But existing coal plants are to keep operating illegally and the draft is furtive about coal-to-biomass plans.
Read moreNew report – deadly legal breaches by Western Balkan coal plants increased in 2022
Press release | 28 June, 2023In 2022, deadly air pollution from the Western Balkans’ coal power plants increased compared to 2021, according to the fifth edition of Bankwatch’s Comply or Close report, published today (1). Emissions of all three regulated pollutants – sulphur dioxide (SO2), dust and nitrogen oxides (NOx) grew, and for the first time, the region’s overall limit for NOx was breached.
Read moreSerbia: Complaints over illegal operation of Morava coal power plant
Press release | 23 June, 2023A complaint by the Renewables and Environmental Regulatory Institute (RERI) and CEE Bankwatch Network (1) challenging Serbia’s failure to comply with pollution control rules under the Energy Community Treaty was recorded yesterday by the the Energy Community Secretariat in Vienna (2).
Read moreRelated publications
High risk of corruption in Sostanj TES 6: Report by Slovenian Commission for the Prevention of Corruption (unofficial translation)
Official document | 23 February, 2012 | Download PDFFor many years TES 6 has been surrounded by rumours of corruption. In February 2012 the Slovene State Commission for the Prevention of Corruption published a report stating that acts of corruption could have influenced the awarding of the contract to French company ALSTOM and that the law on the state guarantee itself was initially drafted by employees of HSE, the owner of the Sostanj power complex. Slovene NGO Focus Association for Sustainable Development has translated the report to English. (The original report (in Slovenian language) is available for download here (pdf).)
Complaint to EBRD’s Public Complaint Mechanism: The Sostanj thermal power plant project
Official document | 17 January, 2012 | Download PDFBankwatch, Slovenian NGO Focus and Environmental Legal Service (CZ) ask the EBRD’s Project Complaint Mechanism to undertake a compliance review of whether the bank has complied with its Environmental and Social Policy 2008 in relation to two aspects of the Sostanj lignite thermal power plant: (a) Claims by the EBRD that the project in question is “CCS ready” and (b) the EBRD’s assessment of whether Slovenia can fulfil its obligations in meeting long-term EU climate goals if it undertakes the project.
Complaint regarding Sostanj TES6: CCS, public procurement, economic vialbility
Official document | 9 January, 2012 | Download PDFThe complaint, filed with the European Investment Bank by Environmental Law Service (CZ) and Focus Association for Sustainable Development (SI), outlines controversies in relation to the Sostanj lignite thermal power plant with regards to the following aspects: insubstantial allegation that the project is „carbon capture ready“ and that the assessment submitted by the operator fulfils the criteria set up by the relevant EU Directive, failure to comply with the relevant EU directive for public procurements, questionable economic viability of the project.