North Macedonia relies predominantly on fossil fuels (low-grade lignite and gas) and hydropower, and is dependent on electricity imports. The total generation of electricity in 2022 was 5,634 GWh, and another 1,471 GWh was imported to satisfy the total domestic electricity demand.
The electric power generation capacity in North Macedonia in 2022 mainly consisted of two coal thermal power plants with a total of 824 MW installed capacity, nine large hydropower plants with 571 MW installed capacity, 123 small hydropower plants with 148 MW installed capacity and three gas CHP plants with 287 MW installed capacity. In 2021 and 2022, the long-dormant Negotino heavy fuel oil plant was also fired up in response to the energy crisis that hit the country but made only a small contribution to overall production.
In January 2020 the government adopted the Energy Development Strategy 2020-2040 which elaborates three different scenarios: reference (business as usual), moderate transition and green (strong decarbonisation) scenarios. The moderate transition and green scenarios both foresee coal phase-out in 2025 which makes it the first country in the Western Balkans to layout concrete options for a pre-2030 coal phase-out.
The smaller thermal power plant REK Oslomej had been operating occasionally during winter months. Discussions about “urgent need for modernization of the obsolete equipment” have been going on for years now, but according to the Energy Strategy it is phased out in all three scenarios. It will be replaced by a 120 MW PV plant on top of the now depleted lignite mine.
In the moderate transition and green scenarios in the Strategy, phase out of the РЕК Bitola lignite-fired power plant in 2025 is also recommended. In the reference scenario investments for modernization and pollution control are given instead of phase out.
North Macedonia adopted its first National Energy and Climate Plan (NECP) in June 2022. It follows the more progressive scenarios from the Energy Strategy in its coal phase-out timeline, with Oslomej being decommissioned in 2021 and Bitola in 2027. However, in the introduction it also says that the timeline may slip to 2029.
These ambitious phase-out dates are mainly due to a lack of economically viable coal supply. There are two operational open cast lignite mines – Suvudol and Brod-Gneotino. According to North Macedonia’s 2023 Just Transition Roadmap, Suvodol has enough coal for two years and Brod-Gneotino for ten years the way they currently operate.
However, reality is not following the NECP. According to the state owned electricity company ESM’s 5-year investment plan 2018-2022, the commissioning of a new Zivojno mine could extend the coal supply to TPP Bitola for another ~10.6 years. This would obviously prevent North Macedonia from achieving a timely coal phase-out.
In addition, the NECP foresees the construction of the controversial Cebren pumped storage plant or a 250 MW fossil gas power plant at the site of the existing Bitola coal plant. However, ESM is planning both of these — although as of January 2024, the Cebren plant appears to be on the rocks. In addition, plans for additional gas plants at Negotino and Skopje have also been announced, which do not appear in the Energy Strategy or NECP.
Fossil gas is imported through a single entry point at the Bulgarian border. Gas is mainly consumed by industrial customers and the three CHP plants, while households have an almost negligible share of total consumption due to the very limited spread of distribution networks and the relatively high cost of gas.
In recent years, an additional gas pipeline to bring gas from Greece to North Macedonia has been heavily promoted by the North Macedonian government, and in December 2021 the European Investment Bank and Western Balkans Investment Framework approved financing for the project. In autumn 2022 the European Bank for Reconstruction and Development also announced that it was considering financing. Despite the obvious weaknesses of increasing dependence on imported fossil fuels, as of January 2024, North Macedonia’s government has shown no signs of reconsidering the pipeline project.
Under Energy Community Treaty commitments to increase the share of renewable energy in its mix, North Macedonia had a target of 28 per cent in gross final energy consumption in 2020. In April 2017 North Macedonia amended its National Renewable Energy Action Plan submitted to the Energy Community in 2012, to take into account lower biomass baseline data (17.2% compared to 21.2% originally). Based on the revised biomass statistics, the 2020 target for the share of renewable energy sources in gross final energy consumption was changed from 28 per cent to 23 per cent. The Energy Community’s Ministerial Council adopted a decision approving this revision in November 2018. The share of renewable energy in gross final energy consumption in 2020 stood at 19.2 per cent, still a long way from the target.
North Macedonia has a 36.8 MW wind farm at Bogdanci and has received EU and KfW financing to expand it. It was the first country in the Western Balkan region to put into operation a sizeable wind facility. Its second wind farm, the 36-MW Bogoslovec, only started operating in mid-2023.
Solar PV capacity reached reached 144 MW by the end of 2022, and continued to grow rapidly during 2023. All estimates so far show that the country has significant additional capacity, even when biodiversity is taken into account.
Source | Solar PV | Wind |
IRENA, 2020
REmap, 2030 potential minus 2015 installed |
1104 MW
1624 GWh |
552 MW
1635 GWh |
IRENA, 2017
Additional cost-competitive potential up to 2050 |
1463 MW
2214 GWh |
4883 MW
7569 GWh |
SEERMAP
Decarbonisation scenario 2050 minus 2016 |
1297 MW
1696 GWh |
1118 MW
2134 GWh |
North Macedonia Energy Strategy
Green Scenario to 2040 |
1357 MW | 713 MW |
North Macedonia draft NECP
to 2030 |
750 MW | 686 MW (600 without incentives) |
Around 106 small hydropower plants have gone online since 2010, and, like other countries in the region, North Macedonia has plans for more large hydropower. The Energy Development Strategy recommends a total of 998 MW new hydro capacity to be added until 2040 in all scenarios.
North Macedonia has plenty of room for energy efficiency improvements. Electricity distribution losses amounted to 13.5 per cent in 2022, and practices such as heating with old-style electrical heaters have contributed to increasing energy costs for many households.
In December 2022, the Energy Community Ministerial Council adopted 2030 climate and energy targets. According to these, North Macedonia needs to achieve a 38 per cent share of renewables in gross final consumption of energy, and to reduce its greenhouse gas emissions by 82 per cent compared to 1990 levels – requiring a significant decrease from the levels of recent years. To boost energy efficiency and energy savings, it also needs to cap primary energy consumption at 2.3 Mtoe and final energy consumption at 2.0 Mtoe by 2030.
For a more in-depth look at barriers to a sustainable energy transition in North Macedonia and our proposals for how to overcome them, see our 2021 study with the Friedrich Ebert Stiftung: The Political Economy of Energy Transition in Southeast Europe – Barriers and Obstacles.
More on coal in the Balkans
Sustainable district heating gives hope to the Romanian city of Motru, in a coal mining region
A new study shows that the city’s district heating can come from fully renewable sources.
Read more
Bosnia and Herzegovina illegally extends lifetimes of deadly coal plants
Yesterday the Federation of Bosnia and Herzegovina’s Parliament voted to extend the lifetime of the antiquated Tuzla 4 and Kakanj 5 coal units, in clear breach of the Energy Community Treaty. The move condemns the public to yet more lethal air pollution.
Read more
The heroic dust monitor
This year we are marking five years since Bankwatch engaged in air pollution work in the Balkans. Throughout these years, there was one constant in the work – the environmental dust monitor. It has become the hero of many communities and is known to every organisation in the region that works for cleaner air.
Read more