Rovinari unit 7, Romania
The Romanian Government has been negotiating for several years with the Chinese Government to build a new 600 MW unit at the lignite power plant in Rovinari, Gorj County. The new unit would be built on the site of Units 1 and 2, currently decommissioned. A new up and running plant would pollute the whole region for at least 40 more years, a coal plant’s average lifespan.

Stay informed
We closely follow international public finance and bring critical updates from the ground.
Background
In December 2012 Oltenia Energy Complex (state owned company) signed a memorandum of understanding with China Huadian Engineering Co. Ltd for setting up a project company and the construction of a 500 MW lignite-fired unit at Rovinari. The initial information was that the new unit would be built at an estimated cost of one billion euros. Since then, more memorandums of understanding have been signed between the Romanian and the Chinese company or the respective Governments, laying down the steps to create a Romanian-Chinese joint-venture, which would implement the project. The most recent one dates to September 2015, when it was reported that the unit would have an installed capacity of 600 MW and would cost EUR 847 million. The project team has met since them, the latest visit of a Chinese delegation to Rovinari taking place in August 2017.

In January 2013, the general manager of the Oltenia Energy Complex said the new unit will export the electricity to Austria and Turkey. China Huadian conducted a pre-feasibility study in 2014 for the construction of this unit at Rovinari, indicating the need to dismantle some of the existing infrastructure, something that would increase the costs of the project and which the representatives CE Oltenia disagreed with at the time. In addition, China Huadian Engineering Co. requested customs exemptions for equipment imported from China, demanding at the same time a long term power purchase agreement or a guaranteed price for coal, which, under European legislation, may be considered illegal state aid. China Huadian would ensure the full financing of the investment, being the main shareholder of the joint venture IPP (Independent Power Producer) that would be created and CE Oltenia would have a share of under 9%.
If the project went ahead, the new unit would be located next to the town of Rovinari, increasing existing air pollution levels from the other 4 units. The lignite would be supplied from the nearby open-pit mines – Tismana I and II, Rosia, Pinoasa, all owned by the same Oltenia Energy Complex – which would require expansion of production capacity. Extending these mines would mean clearing huge land areas, in most cases accompanied by massive deforestation.

Since 2012, Bankwatch Romania has filed a series of complaints in court, requesting the annulment of illegally issued deforestation permits and mine expansion permits which did not assess impacts on the environment. Almost all the actions have been successful in court. After an infringement procedure was initiated by the European Commission, all expansions were reassessed. However, the new permits fail to evaluate the cumulative impact of the mines, and are therefore again the subject of Bankwatch Romania court action, one of them being currently suspended. To date (May 2018) no environmental impact assessment procedure has been launched.
In short:
The existing power plant: – Part of Oltenia Energy Complex – 4 units installed every 330 MW each – Three functional units: 3, 4 and 6; unit 5 undergoing modernisation – Location: southwestern Romania, Gorj county – Year of commissioning: 1972 – Fuel used: lignite – Environmental integrated permit expired on 31.12.2017
New power plant – China Huadian + CEOltenia – 1 unit of 600 MW – Fuel: lignite (6 million tonnes per year) – Life expectancy: 40 years – Significant social and environmental impacts
Latest news
Dobrovoľne behali okolo uhoľnej elektrárne. Uprostred panorámy sa objavil obrovský hríb dymu, hovorí bežec
Bankwatch in the media | 14 January, 2021Skupina bežcov sa rozhodla zabehnúť trasu okolo uhoľnej elektrárne v Severnom Macedónsku, aby poukázali na znečistenie ovzdušia v okolí.
Read moreRunners raise the alarm about air pollution from coal power during inaugural Lung Run
Blog entry | 22 December, 2020One of the leading reasons for the extremely polluted air are the outdated and substandard coal-fired power plants in the region. The 16 plants operating in the Western Balkan countries emit as much sulphur dioxide and dust pollution as the entire fleet of coal plants in the EU.
Read moreTime to end the damaging cycle of land, surface and groundwater pollution in Tuzla
Blog entry | 21 December, 2020There are few things one can be sure of in life, but the constant anxiety communities near Bosnia-Herzegovina’s Tuzla power plant experience is one of them.
Read moreRelated publications
Lifting the smog
Study | 25 June, 2019 | Download PDFHow much Tuzla’s public health would benefit from enforcement of air quality legislation CEE Bankwatch Network and the Center for Ecology and Energy have therefore undertaken independent monitoring in Tuzla of coarse dust particles known as PM10. Toget
Policy on corporate loans based on PCM CRR on the EPS Restructuring project
Advocacy letter | 6 May, 2019 | Download PDFThe PCM has finalised the Compliance Review Report (CRR) of the EPS Restructuring project and has closed the case without further monitoring. We welcome the recommendation that clarification of the policy framework and strategic guidance are urgently r
Retrained and forgotten
Study | 16 April, 2019 | Download PDFThis research analyses the context of downsizing the ining sector in the Jiu Valley, the concrete measures taken to mitigate the social impact in the areas hit by restructuring the mining sector and how successful these measures were.