Legal opinion on the possible financing scheme of Plomin C and its compatibility with EU rules on state aid and public procurement (public summary)
Briefing | 5 May 2014
This legal analysis argues that the tender arrangement for the Plomin C coal-fired power plant seriously questions the feasibility of the entire investment, not just from an environmental point of view as demonstrated by Zelena Akcija beforehand, but by now also from a competition point of view.
The analysis was prepared by legal experts from the Environmental Management and Law Association (EMLA).
The prequalification document for the Plomin C tender procedure is available for downloaded as pdf.
Theme: Energy & climate | Social & economic impacts
Location: Croatia
Project: Plomin coal power plant, Croatia