The European Anti-Fraud Office (OLAF) decided to start an official investigation into the case of the Sostanj lignite power plant in Slovenia due to serious concerns about corruption and conflicts of interests in the granting of the contract to the company Alstom.
(Information on OLAF staff has been blackened on request by the Office.)
Theme: Energy & climate
Location: Slovenia
Project: Sostanj lignite thermal power plant unit 6, Slovenia