• Skip to primary navigation
  • Skip to main content
  • Skip to footer

Bankwatch

  • About us
    • Our vision
    • Who we are
    • 30 years of Bankwatch
    • Donors & finances
    • Get involved
  • What we do
    • Campaign areas
      • Beyond fossil fuels
      • Rights, democracy and development
      • Finance and biodiversity
      • Funding the energy transformation
      • Cities for People
    • Institutions we monitor
      • European Bank for Reconstruction and Development
      • European Investment Bank
      • Asian Infrastructure Investment Bank
      • Asian Development Bank (ADB)
      • EU funds
    • Our projects
    • Success stories
  • Publications
  • News
    • Blog posts
    • Press releases
    • Stories
    • Podcast
    • Us in the media
    • Videos

Home > Press release > Europe’s public banks disburse EUR 650 million to Sostanj coal plant despite ongoing corruption charges

Europe’s public banks disburse EUR 650 million to Sostanj coal plant despite ongoing corruption charges

Ljubljana – The European Investment Bank announced today [1] that it would pay the remaining EUR 440 million out of a EUR 550 million loan [2] for the construction of a new 600 megawatt lignite unit at Sostanj [3] in Slovenia, and that the European Bank for Reconstruction and Development would follow suite with its parallel EUR 100 million loan.

8 March 2013

Ljubljana – The European Investment Bank announced today [1] that it would pay the remaining EUR 440 million out of a EUR 550 million loan [2] for the construction of a new 600 megawatt lignite unit at Sostanj [3] in Slovenia, and that the European Bank for Reconstruction and Development would follow suite with its parallel EUR 100 million loan.

The news comes in spite of assurances from EIB President Werner Hoyer during a press conference last week in Brussels that corruption allegations would be scrutinised before any further payments to the project are made. Despite Hoyer’s commitments, the money will be paid before the European Anti-Fraud Office (OLAF) [4] has completed its investigation into allegations of corruption about the awarding of the constructing contract for the new plant to Alstom, the French infrastructure conglomerate. Additionally, the public has yet to be informed about the outcomes of similar internal investigations at the EIB and EBRD [5].

“This is all really bad news for Slovenia,” comments Barbara Kvac from Slovenian NGO Focus. “This plant alone will take up almost all of the allowed emissions for our country if we align to the EU 2050 climate goals. It is ironic that the bank of the European Union is lending Slovenia money that will make reaching EU objectives more difficult, and it is sad that in Slovenia we cannot count on coherent, positive cues from our country for Brussels.”

“Since the EIB approved its loan in 2007 and the EBRD followed in 2010, Sostanj has become a huge scandal that has followed the banks. Despite the damaging climate impact, the embarrassing corruption scandal and the questionable economic viability of the project, the EIB and EBRD signed the deal with the Slovenians and couldn’t see itself pulling out,” said CEE Bankwatch Network’s Pippa Gallop. “But the EIB and EBRD are the first institutions that should be courageous enough to pull out if a deal is deficient: they are public banks, meant to uphold European goals. Last time I checked, pollution, corruption and dubious economics were not EU objectives.”

Coincidentally the disbursement follows the release of a new report by the Health and Environment Alliance “The unpaid health bill – how coal power plants make us sick,” which provides the first-ever calculations of the effects of coal-fired power generation on chronic lung disease and some heart conditions.

“The findings of the report come as no surprise, since Greenpeace issued a report with similar findings already in June 2012. HEAL’s report confirms the worst. The TES 6 project will lock Slovenia into a fossil-fuel intensive future for the next 40 years, and this could eat up around 9 billion euros of taxpayers money in the form of health costs associated with air pollution from coal power plants. If we add the possible risks that this project brings with its bad economics and vulneribility, this number could be even much higher,” said Nina Štros, head of Greenpeace CEE in Slovenia. „It is outrageous that the EIB would rather protects its own interests and the interests of the investor rather than working towards what it was established for: creating a better and safer future for all Europe’s people.”

Notes for the editors:

1. http://www.eib.org/infocentre/press/news/all/eib-and-ebrd-to-support-completion-of-tes-thermal-power-plant-sostanj-project.htm

2. 110 million euros have already allegedly been paid out by the EIB in 2011 according to media reports. http://www.eib.org/projects/pipeline/2006/20060319.htm

3. https://bankwatch.org/our-work/projects/sostanj-lignite-thermal-power-plant-unit-6-slovenia

4. https://bankwatch.org/publications/olaf-decision-investigate-corruption-tes-6

5. https://bankwatch.org/sites/default/files/StateCommissionReport-corruption-TES6-23Feb2012.pdf

For more information contact:

Lidija Zivcic,
Focus Slovenia
Email: lidija at focus.si
Mobile: +386 41 291091

Nina Stros, Head of Greenpeace CEE in Slovenia
Email: nina.stros at greenpeace.si
Mobile +386 40 871 530

Never miss an update

We expose the risks of international public finance and bring critical updates from the ground – straight to your inbox.





Institution: EBRD | EIB

Theme: Energy & climate

Location: Slovenia

Project: Sostanj lignite thermal power plant unit 6, Slovenia

Tags: coal | energypolicy | fossil fuels

Footer

CEE Bankwatch Network gratefully acknowledges EU funding support.

The content of this website is the sole responsibility of CEE Bankwatch Network and can under no circumstances be regarded as reflecting the position of the European Union.

Unless otherwise noted, the content on this website is licensed under a Creative Commons BY-SA 4.0 License

Your personal data collected on the website is governed by the present Privacy Policy.

Get in touch with us

  • Bluesky
  • Email
  • Facebook
  • Instagram
  • LinkedIn
  • RSS
  • YouTube