The EBRD must stay away from the unsustainable conversion of Tuzla’s coal plant and prioritise renewables in the district heating sector
November 9, 2022
This briefing offers an overview of the European Bank for Reconstruction and Development’s (EBRD) ongoing assessment of whether to grant a EUR 50 million loan in order to replace unit 3 of the Tuzla coal plant with a waste and biomass incineration syst
Red flags over plans to swap coal for biomass and waste incineration in Tuzla
September 8, 2022
The European Bank for Reconstruction and Development (EBRD) and Bosnia and Herzegovina’s energy utility Elektroprivreda BiH are signing today an agreement formalizing the Bank’s commitment to consider financial support for a particularly questionable energy project in Tuzla. But the public is barely aware of what this risky investment could bring to local communities.
Bosnia’s planned Tuzla 7 lignite plant on the rocks after state aid U-turn
July 6, 2022
The future of the planned 450 MW Tuzla 7 lignite plant in Bosnia and Herzegovina is again in doubt after the country’s State Aid Council revoked its decision to approve a public guarantee for a EUR 614 million loan from China Eximbank last week, four years after the Council’s initial clearance.
Ministarsko vijeće EZ potvrdilo: Garancija za kredit za blok 7 TE Tuzla nezakonita
December 3, 2021
Državna garancija za kredit za izgradnju novog bloka 7 termoelektrane Tuzla je nezakonita prema Ugovoru o Energetskoj zajednici (EZ), …
Energetska zajednica utvrdila – Državna garancija za kredit namijenjen gradnji Bloka 7 TE Tuzla nije zakonita
December 3, 2021
Ministarsko vijeće Energetske zajednice (EZ) je utvrdilo da državna garancija za kredit namijenjen izgradnji Bloka 7 termoelektrane Tuzla …
Block 7 of the Tuzla thermal power plant in Bosnia & Herzegovina is illegal
December 2, 2021
The guarantee for the public loan for the planned Block 7 of the Tuzla thermal power plant in Bosnia & Herzegovina is illegal according to …
Ministarsko vijeće zvanično potvrdilo: Garancija za Blok 7 nezakonita
December 1, 2021
Državna garancija za kredit kineske Eximbanke za izgradnju novog Bloka 7 TE Tuzla je nezakonita prema Ugovoru o Energetskoj zajednici, …
POTVRĐENO: Nezakonita garancija za kredit za blok 7 termoelektrane Tuzla
December 1, 2021
Ukoliko se realizuje, projekat bi spriječio Bosnu i Hercegovinu da ispuni obaveze dekarbonizacije svoje ekonomije u narednim decenijama.
Loan guarantee for Bosnia’s Tuzla 7 coal plant confirmed as illegal
December 1, 2021
Energo – CEE/FSU Power
Bosnia and Herzegovina, Advisory Committee had submitted an official opinion in the case against Bosnia and Herzegovina
November 22, 2021
The Secretariat of the Energy Community (EnC) said that the Advisory Committee had submitted an official opinion in the case against Bosnia …