The Republika Srpska government plans to build a new 350 MW lignite power plant in Gacko, near the town’s existing plant. After years of stagnation, in August 2022 it was reported that the Czech company Witkowitz was considering investing in the project.
Stay informed
We closely follow international public finance and bring critical updates from the ground.
Background
In December 2017, a Memorandum of Understanding was signed between state-owned utility Elektroprivreda Republike Srpske, the China Machinery and Engineering Corporation (CMEC) and Emerging Markets Power Fund, to build a new 350 MW lignite power plant in Gacko, near the town’s existing plant. After years of stagnation, in August 2022 it was reported that the Czech company Witkowitz was considering investing in the project. However, it is still unclear where financing would come from.
As is too often the case in southeast Europe, there has been no convincing analysis proving that this plant is needed or that it would be the best way to provide Bosnia-Herzegovina’s energy supply in the coming years.
In April 2018 an analysis by economist Damir Miljević showed that fatal flaws in the input data make it highly likely the plant will generate losses. Three out of the main data inputs for the official feasibility study – the price of coal, electricity sales price, and the price of CO2 – are unrealistic:
- A realistic price of coal is mentioned in the study as just over EUR 18 per tonne – yet the amount used in the calculation is much lower, around EUR 13.3 per tonne.
- The Study foresees export of all the electricity generated, at a price of EUR 50 per MWh, except in exceptional cases when 30% would be sold on the domestic market at EUR 19.90 per MWh. There no evidence that the electricity would find a market in the long term and that it could be sold at this price. Moreover, the scenario including 30% of electricity being sold domestically is not even examined in the calculation – if it was it would show that the plant is unprofitable.
- A CO2 price of EUR 5 per tonne is mentioned in the text, but not included in the feasibility calculation. Including even this very low CO2 price in the calculation would take the plant into the realm of unprofitability.
The analysis concludes that although the official feasibility study for Gacko II claims it would generate profit of around EUR 23 million per year, with more realistic input data, a loss of minimum EUR 1.15 million per year looks more likely.
By now the study is also very much out of date, and the impacts of the EU’s planned Carbon Border Adjustment Mechanism would need to be taken into account for any electricity planned for export.
A March 2023 study by IEEFA found that Gacko II would become a stranded asset under several scenarios, even with generous assumptions that favour lignite generation, and that financing for the project is uncertain. The study also found that investing in onshore wind and utility-scale solar PV would offer safer and improving returns, quicker construction and cleaner power, as well as better access to financing.
In October 2023, an environmental impact assessment process began for the project, and a public consultation on the study was held in 2025. As of January 2026, it does not seem to have been approved.
Latest news
Western Balkans gets second chance at just transition: Can new support platform deliver?
Blog entry | 15 July, 2026For coal-dependent communities in the Western Balkans, the launch of the JET Balkans project marks a welcome end to more than two years without a dedicated regional support platform. But with political commitment, funding and transparency still in short supply, local authorities and civil society are wondering whether the initiative can turn planning into meaningful implementation, or whether it will repeat the shortcomings that have slowed just transition efforts across the region.
Read moreWestern Balkans coal plants continue to breach pollution limits despite legal deadlines, report says
Bankwatch in the media | 8 July, 2026Coal-fired power plants across the Western Balkans emitted sulphur dioxide at more than six times legal limits in 2025, with dust pollution reaching its worst level since current emissions rules came into force eight years ago.
Read moreWestern Balkan governments must finally penalise illegal coal pollution – new report
Press release | 22 June, 2026In 2025, systematic law enforcement failures allowed sulphur dioxide (SO2) emissions from the Western Balkans’ ageing coal power plants to exceed legal limits by 6.6 times, according to the eighth edition of Bankwatch’s Comply or Close report, published today (1). Nitrogen oxides (NOx) emissions also continued to breach legal limits, while dust pollution increased, reaching the highest level since the current rules entered force in 2018.
Read moreRelated publications
The EBRD, KfW, coal and corruption: European money in the Kolubara mine in Serbia
Briefing | 12 March, 2013 | Download PDFLinked to a slew of controversies, the Kolubara lignite mining project in Serbia is in line for support from European public banks. Corruption allegations, pollution at local level, irregularities in resettlement of local populations and not to forget a climate damaging approach to energy investments should be reason enough to find alternative options.
Kolubara mine “mired in crime and corruption”
Bankwatch Mail | 7 March, 2013 |At a press conference in January, Serbia’s energy minister Zorana Mihajlović spoke out strongly against the Kolubara mining complex, describing it as being “mired in crime and corruption” while also announcing that a thorough investigation is ongoing into corrupt practices by the Kolubara management. Bankwatch believes that this latest confirmed scandal at Kolubara should be giving the EBRD serious pause for reflection as it considers yet another loan to the Serbian electricity company EPS, heavily implicated in these latest revelations.
EBRD enters Kosovo: Past IFI failures must be heeded
Bankwatch Mail | 7 March, 2013 |Kosovo has just celebrated the fifth anniversary of independence. In these five years, Kosovo has achieved membership of certain international financial institutions (IFIs): having already joined the IMF and the World Bank, on December 17 last year Kosovo became the 66th member of the European Bank for Reconstruction and Development. Yet what can Kosovo’s citizens expect from EBRD membership?