Gacko II, Bosnia and Herzegovina
May 15, 2018
The Republika Srpske government plans to build a new 350 MW lignite power plant in Gacko, near the town’s existing plant. After years of stagnation, in August 2022 it was reported that the Czech company Witkowitz was considering investing in the project.
Kamengrad lignite power plant, Bosnia-Herzegovina
May 15, 2018
An idea to build a power plant at the open-cast Kamengrad coal mine near Sanski Most in the Federation of Bosnia and Herzegovina has been around for years, but in November 2017 it took a step forward with the signing of a Memorandum of Understanding between Energy China International and the construction supplier Lager d.o.o. for a 2 x 215 MW plant.
Planned Gacko II lignite plant in Bosnia-Herzegovina likely to make losses, shows new analysis
April 12, 2018
Our colleagues from the Center for Environment from Banja Luka have today published a new analysis of the feasibility study for the planned Gacko II lignite power plant in Bosnia-Herzegovina, which shows that the new plant is likely to be unprofitable.
Mounting pressure to revoke permit for the planned thermal power plant Ugljevik III
March 21, 2018
In contrast to the global trend of decreasing coal from the energy mix, the Western Balkan countries are stubbornly planning a whole fleet of new lignite plants, most of which are plagued by breaches of environmental laws. The latest case in point is the planned 600MW Ugljevik III.
Ponovo razmotriti planove
August 19, 2017
Države koje planiraju nove elektrane na ugalj, među kojim je i Crna Gora, moraju ponovo da razmotre investicione planove, kao i finansijske implikacije ovih projekata kako bi se osiguralo da su oni zaista u skladu sa novim, strožim standardima EU, poka
Nove TE teško do EU standarda
June 14, 2017
Bankwatchova analiza obuhvata osam termoelektrana planiranih u Bosni i Hercegovini, Kosovu, Makedoniji, Crnoj Gori i Srbiji, kao i postrojenje Stanari u BiH, koje je počelo da radi u septembru prošle godine Source: Nove TE teško do EU standarda – Vijes
Analiza /Ekologija ili ekonomija: Za i protiv gradnje termoelektrana u BiH
March 31, 2017
Koji su argumenti za i protiv gradnje novih termoelektrana u BiH Source: Analiza /Ekologija ili ekonomija: Za i protiv gradnje termoelektrana u BiH / Radio Sarajevo
Overlooked carbon costs spell financial trouble for Western Balkan coal power plants
March 29, 2017
Ten coal-fired power plant projects across the Western Balkans are facing serious financial problems as they have not taken properly into account carbon costs, according to analysis from environmental pressure group Bankwatch. Source: bne IntelliNews –
Co dalej z polskim OZE? Spalanie biomasy drzewnej wcale nie takie ekologiczne – Gospodarka
March 23, 2017
Polska zobowiązała się do osiągnięcia do 2020 roku 15-procentowego udziału odnawialnych źródeł energii w całości wykorzystywanych przez nas surowców energetycznych. Jednym z takich odnawialnych źródeł może być biomasa, ale niepochodząca z drewna, mówi
Kaspický plyn naráža na ceste do Európy na ľudské práva
March 16, 2017
Nad diverzifikáciou dodávok plynu do Európy visí čoraz viac otáznikov. Source: Kaspický plyn naráža na ceste do Európy na ľudské práva – euractiv.sk