Banovici lignite power plant, Bosnia and Herzegovina
The 350 MW Banovići coal power plant project was planned alongside the existing Banovići mine just a few kilometres away from Tuzla by the predominantly state-owned RMU Banovići (Banovići Brown Coal Mines).
Stay informed
We closely follow international public finance and bring critical updates from the ground.
Background
The 350 MW Banovići coal power plant project was planned alongside the existing Banovići mine just a few kilometres away from Tuzla by the predominantly state-owned RMU Banovići (Banovići Brown Coal Mines). In 2015, a construction contract was signed with China’s Dongfang, the same company which built the Stanari plant. As of early 2024 it seems highly unlikely that the plant will go ahead, but it has not been officially cancelled.
Mystery economics
The project’s economics have been kept under wraps and no feasibility study is publicly available.
Financing was sought from the Industrial and Commercial Bank of China (ICBC), but was never signed. The project is supposed to cost EUR 405 million. It also appears that a guarantee by the Federation of BiH government would be required, raising questions about compliance with State aid rules under the Energy Community Treaty.
'Hostages of coal'
An AlJazeera report on the situation of people affected by the coal infrastructure in Tuzla and Banovici.
Local language only.
Legal violations
The environmental permit for the Banovići power plant was renewed in early 2016, but failed to cover numerous issues and prescribe precise mitigation measures. NGO Ekotim therefore filed a court case seeking to annul the permit in April 2016. The court case was rejected in late 2019 on the spurious grounds that a Sarajevo-based NGO cannot complain about a project sited near Tuzla – a verdict that was appealed at the Federal Supreme Court, as well as being subject to a complaint to the Aarhus Convention. Before the court ruled on the case, the permit expired in early 2021, and does not appear to have been renewed.
No transboundary consultation was carried out for the plant’s environmental assessment, even though this is required under the Espoo Convention. After a complaint was made to the Convention’s Implementation Committee, Bosnia and Herzegovina pledged to carry out transboundary consultations for any renewal of the plant’s environmental permit.
Scarce water resources
In order to obtain water for the Banovići plant, the small existing Ramići lake would be expanded into a larger reservoir. However it is not clear that the runoff from the surrounding hills could provide enough water. Another issue is the structural soundness of the earth dam which is planned to hold back the water at Ramići.
Initial proposals included using water from the Turija river to fill the reservoir during dry periods, however this would then deprive Modrac, and thus the Tuzla power plant and the people of Tuzla, of a significant source of water. More recent proposals have focused on taking water from Lake Breštica which is located in the Spreča river basin, but this would have the same result. The issue remains unsolved. For this reason Ekotim filed a court complaint against the environmental permit for the reservoir in April 2016, which was also rejected in late 2019 and was appealed to the Federal Supreme Court.
In September 2019 it was reported that RMU Banovići had failed to obtain a water consent for the Ramići reservoir from the Tuzla cantonal authorities, as it had tried to extend the validity of a previous one which had already expired.
Construction permit refused
The project has received on-and-off high level support from the Federal authorities in Bosnia-Herzegovina. However in December 2017, it was announced that the project had been refused a preliminary construction permit due to unresolved issues around water consumption, coal supply, flue gases, ash disposal and other issues.
Latest news
Illegal coal subsidies could cost south-east European countries dearly, warns new study
Press release | 8 June, 2015Prague – New investments in coal mines and power plants could cost the Western Balkans and Ukraine dearly if they fail to take into account binding rules on subsidies (State aid), according to a new briefing released today by CEE Bankwatch Network.
Read moreWestern Balkans electricity plans: where will all that power go?
Blog entry | 23 March, 2015Western Balkan countries have ambitious plans to increase their electricity generation over the next years. But what will happen if they all become a regional energy hub? Will there be a demand for all the available electricity?
Read moreElectricity export ambitions may prove risky for Western Balkans, shows new study
Press release | 19 March, 2015The Western Balkans countries have strong electricity export ambitions that create the danger of stranded assets, finds a new report launched by CEE Bankwatch Network today. If governments take electricity expansion decisions without taking due account of developments in other countries, the region will have to compete with other nearby exporters and may find that its power plants become uneconomic.
Read moreRelated publications
Comply or Close 2024: six years of deadly legal breaches by Western Balkan coal plants
Report | 17 September, 2024 | Download PDFThe end of 2023 marked six years since the deadline passed for power plants in the Western Balkans to meet new air pollution standards. Yet the deadly air pollution from the region’s mostly antiquated coal power plants has hardly decreased at all since 2018.
Western Balkan coal power plants polluted twice as much as those in the EU in 2019
Briefing | 12 July, 2021 | Download PDFThe non-compliance of Western Balkan coal power plants with the emission limits enshrined in the Energy Community Treaty is reflected in the region’s high sulphur dioxide (SO2), nitrogen oxides (NOX) and dust emissions. This briefing looks mainly at th
The great coal jobs fraud (2018 UPDATE)
Study | 28 June, 2018 |This study, an update of our November 2016 analysis, examines the claims and finds that in almost all cases, they are exaggerated. In fact, even the current levels of employment cannot be maintained and some companies such as Elektroprivreda Srbije and