Protecting rivers and communities in southeast Europe
Southeast European governments are pushing a wave of hydropower projects that are damaging pristine rivers, including in protected areas. Over more than a decade, together with our partners we’ve successfully steered European public financing towards more sustainable solutions in the region. But plenty of plans remain, particularly large dams.
The Zalomka river in Bosnia and Herzegovina would be dammed by the Dabar hydropower plant
Stay informed
We closely follow international public finance and bring critical updates from the ground.
Key facts
- Large dams have long been part of the region’s energy mix, but in the last 20 years, a wave of small hydropower plants has been built, mainly by private companies driven by renewable energy incentives.
- Although much smaller, the cumulative impact of these plants is ‘death by 1000 cuts’, as they are usually built in the most remote, pristine environments. They caused widespread public resistance across the region, which stopped many projects.
- Our 2015 and 2018 research revealed that the EBRD, EIB and World Bank Group, had been more involved than was initially apparent. In 2018 we identified EUR 727 million in support for 82 hydropower plants across southeast Europe since 2005.
Key issues
- Most hydropower projects in the region have been small ones, supported by commercial banks, sometimes channelling EBRD or EIB money. These loans are kept secret due to ‘commercial confidentiality’.
- After Bankwatch uncovered the impacts of EBRD and EIB hydropower financing in southeast Europe, and campaigned for improvements together with partners like EuroNatur, RiverWatch and Patagonia, in 2019 the banks tightened their standards.
- Due to changes in subsidies rules and public outcry, the wave of small hydropower plants has slowed down – though not yet stopped. But many highly damaging large dam projects remain. Some have no funding secured, but others are financed by the China Eximbank or other opaque institutions.
Background
In the last 25 years southeast Europe has suffered from a wave of hydropower projects.
Bulgaria moved fastest to hand out concessions on small rivers and streams in the late 1990s and early 2000s and was then joined by others. Albania has been the most active in this regard, awarding concessions and approvals for at least 714 hydropower plants since 2002.
The negative social and environmental consequences in Bulgaria and Albania unfortunately did not cause other countries in the region to learn from their experiences. All countries have at various points offered generous feed-in tariffs to hydropower project developers, thus incentivising the construction of plants that would otherwise not be worth building. This led to an upsurge in construction from about 2012 onwards, which in turn led to increasing public resistance.
This was successful in stopping many plants, and under pressure from the public, the EU and the Energy Community Secretariat, the countries have gradually changed their renewable energy incentive rules to either phase out feed-in tariffs completely or limit them to the very smallest plants, in line with EU State aid rules.
While a consensus is gradually emerging in the region that small hydropower is too damaging compared to its disappointing energy output, governments are continuing apace with plans for larger hydropower plants, many of which have been planned for decades.
As the EIB and EBRD have rightly become more cautious about financing hydropower in southeast Europe, due to its increasingly poor economics, environmental and social damage and climate change vulnerability, governments are increasingly looking to companies and banks from further afield, often with low transparency, environmental and social standards.
For example, the China Eximbank is financing a series of plants on the Bistrica river and the Dabar plant, part of the Upper Horizons complex, both in Republika Srpska, Bosnia and Herzegovina. Other major controversial projects such as Buk Bijela in Bosnia and Herzegovina, Komarnica in Montenegro, and Skavica in Albania, remain without financing for now. These plants can still be stopped with enough public outcry and legal challenges. The EU also needs to do more to ensure environmental law is followed in all southeast European countries, both EU Member States and accession countries.
River Helpdesk
Are you trying to protect a river from hydropower or other destructive projects?
Do you need help and advice on preventing financing for the project and/or using international complaint mechanisms?
Do you need to reach the right people in the right places?
Apply for support from our River Helpdesk: helpdesk[at]bankwatch.org
Recommendations
Multilateral development banks
Establish clear no-go zones in protected areas and rivers of outstanding quality, as outlined at banksandbiodiversity.org.
Ensure all projects comply with EU law and take responsibility for project assessment, including for projects carried out via intermediaries.
Pay increased attention to the issue of corruption and politically exposed persons’ involvement in hydropower plant projects.
The European Commission and Energy Community
Prioritise energy efficiency and diversification of renewable energy sources in the region.
Provide increased assistance to countries in completing the transposition and implementation of the Birds and Habitats Directives and Water Framework Directive and in researching baseline biodiversity, hydrology and water quality in the countries.
Refrain from endorsing any greenfield hydropower projects as priority investment projects until environmental governance in the region is significantly improved.
Pay more attention to inappropriate hydropower development and state aid when assessing accession countries’ progress towards the EU.
Governments in the region
Take climate vulnerability into account and shift renewable energy plans to prioritise energy savings and appropriately-sited solar and wind potential.
Adopt system-scale planning on the river basin level for decision-making on hydropower and do more to resolve conflicts with nature protection in spatial plans.
Establish clear no-go zones in protected areas and rivers of outstanding quality.
Complete transposition and implementation of the Birds, Habitats and Water Framework Directive. Improve the quality of environmental impact assessments and carry out Appropriate Assessments and Article 4(7) assessments where needed.
Related projects
Upper Horizons hydropower scheme, Bosnia and Herzegovina
A series of dams, diversion tunnels, hydropower plants and channels will completely change the natural hydrology of eastern Herzegovina and have unpredictable impacts on wetlands, rivers and underground karst.
Ulog and Upper Neretva hydropower plants, Bosnia and Herzegovina
A 35 MW hydropower plant is currently under construction on a pristine section of the Neretva river at Ulog. Seven more plants are also planned further upstream.
Skavica hydropower plant, Albania
Instead of increasing its energy security, Albania is pushing the construction of yet more hydropower. The Skavica project may flood several villages, displace thousands of people and bring the Balkan lynx to extinction
Komarnica hydropower plant, Montenegro
Planned by Montenegro’s state-owned electricity utility EPCG, the need for the Komarnica hydropower plant has never been proven.
Buk Bijela dam and the Upper Drina cascade
Planned as a joint project of public utilities owned by the Republika Srpska entity of Bosnia and Herzegovina and Serbia, Buk Bijela on the upper Drina is being pushed forward in violation of local legislation and international conventions.
Boskov most hydropower plant, North Macedonia
Boskov Most was one of 18 hydropower greenfield projects planned by the North Macedonian government in the Mavrovo National Park. After five years of campaigning, we convinced the European Bank for Reconstruction and Development about the folly of this project and to cancel its EUR 65 million loan. Without its major source of funding, the project lost steam and was discontinued.
Krapska Reka small hydropower plant, Macedonia
Loopholes in the EBRD’s due diligence, together with a lack of assessment and monitoring by Macedonia’s local and central government, has proven to be a lethal combination for the country’s rivers. A prime example is the Krapska Reka small hydropower project. The authorities’ failure to recognise the location as part of the proposed Jakupica National Park, Emerald area and a future Natura 2000 site, on top of poor mitigation measures and construction practices, have caused irreversible damage to this small river valley.
Dabrova Dolina hydropower plant, Croatia
A harmless-sounding mill conversion project on Croatia’s stunning river Mrežnica is a textbook example of how even small hydropower plants can damage protected areas. It also exemplifies the lack of transparency and oversight of investments that the European Bank for Reconstruction and Development channelled through commercial bank intermediaries.
Latest news
EU’s house bank breached environmental standards on Serbia hydropower project
Press release | 14 April, 2023The European Investment Bank (EIB) breached its environmental standards during the approval of the Komalj small hydropower plant in Serbia, the Bank’s Complaint Mechanism has concluded, in a report published today. (1)
Read moreKosovo becomes the first Western Balkan country to stop promoting new hydropower
Blog entry | 28 March, 2023After years of hydropower-related controversies, Kosovo’s long-awaited new Energy Strategy confirms that the government does not support new development in the sector, due to its environmental impacts. It also sends promising signals on carbon pricing and solar and wind development. Still, the country needs to avoid wasting money on coal and gas.
Read moreWestern Balkans: scientists and NGO representatives call for more rivers to be protected as part of the Emerald Network
Press release | 13 February, 2023Today, scientists and non-governmental organisations from 11 countries have published a list of 88 rivers they consider high priority for protection, urging Western Balkan countries that have signed the Convention on the Conservation of European Wildlife and Natural Habitats (Bern Convention) to expand the Emerald Network in the region.
Read moreRelated publications
Kungrad 1-3 wind power project, Uzbekistan
Policy comments | 11 March, 2025 | Download PDFKungrad is one of several large-scale renewable projects featuring extensive transmission lines slated for remote, wild areas in Central Asia – an alarming practice that hinders the sustainable energy transition.
How to interact with development banks lending to hydropower projects in Central Asia: A toolkit for civil society activists
Toolkit | 3 February, 2025 | Download PDFThis toolkit is aimed primarily at civil society organisations in Central Asia tackling the construction of dams or other unsustainable water infrastructure.
The Upper Horizons complex, Bosnia and Herzegovina
Briefing | 18 December, 2023 | Download PDFThe Upper Horizons hydropower complex has been planned since the mid-20th century, and is planned to consist of three plants — Dabar, Nevesinje and Bileća — linked by a series of tunnels and channels. If completed, it would have a devastating impact on the karst ecosystems of eastern Herzegovina and beyond.