Shuakhevi hydropower plant, Georgia
Georgia’s biggest and one of the most controversial hydropower plants is mostly famous for its failures. Two months after becoming operational in 2017 its tunnels collapsed. And after two years of repairs water is leaking from the dam. Shuakhevi hydropower plant (HPP) once promised to bring energy independence to Georgia. Instead it managed to collect an impressive ‘portfolio’ of problems in a wide range of areas: from biodiversity, to gender impacts, to community relations.
Stay informed
We closely follow international public finance and bring critical updates from the ground.
Key facts
Location: Location: Adjaristsqali river in south-western Georgia Two dams, 39 metres and 22 metres high, with an installed capacity of 187 MW with expected electricity output of 452 Gwh, and three diversion tunnels of 5.8, 9.1 and 17.8 kilometers. Total project cost: more than USD 420 million.
Total project cost: USD 417 million
- the EBRD: USD 86.5 million
- the IFC: USD 90 million, 20% equity in the project
- the ADB: USD 90 million (source)
Client: Adjaristsqali Georgia LLC (AGL), a special purpose vehicle established in Georgia for the sole purpose of constructing a cascade of three hydroelectric power plants on the Adjaristsqali river, the first of which will be Shuakhevi HPP. Adjaristsqali Georgia LLC is owned by Norway’s Clean Energy Invest AS (50%), India’s Tata Power (50%).
Key issues
- extensive damage to the local ecosystems following the construction of the hydropower plant. The adequacy of the mitigation and biodiversity offsetting measures in ensuring conservation of valuable habitats and species is questionable.
- Lack of detailed assessment of geological risks threatens both hydropower investments as well as communities living in the shadow of the 2 big dams, 1 wier and 32.7 kilometers of tunnels.
- A failure to safeguard local women residents by conducting proper gender impact assessment and ensuring meaningful participation of women in consultations and decision-making
Background
A press release from the Ministry of Energy of Georgia from 24 June 2017 announced that project construction was completed, claiming that by adding its 187 MW to the total installed capacity of the country “the Shuakhevi HPP project will significantly contribute to Georgia’s path toward energy independence”.
Long after that, the project is still not operational. On-going problems with the tunnels of the project raise questions about the robustness of the project design, impact assessment and implementation, as well as about financiers’ prudence in conducting due diligence before decisions were made on public money spending, and in monitoring of the project implementation.
One of the villages heavily impacted by the construction, submitted a request for problem-solving to the EBRD’s, the IFC’s and the ADB’s respective accountability mechanisms. The complainants have brought up concerns of unmitigated negative impacts on community safety and access to water, as well as of inadequate handling of their grievances by the lenders and the client Adjaristsqali Georgia LLC (AGL).
In view of the continued ambition of the Georgian government to build risky dams and of the lenders like the EBRD to provide public money investments for these projects, Bankwatch and Green Alternative call for a transparent process of compliance review to ensure accountability and lessons learned for the institutions involved.
Environmental impact
A 2017 report commissioned by Green Alternative and cited in the complaint documented extensive damage to the local ecosystems following the construction of the hydropower plant, which destroyed 93 ha of natural habitats – the area 10 times higher than the 9,2 ha estimated in the project’s impact assessment.
Some of the report’s key findings:
River and riparian habitats
Biodiversity offsetting or compensation were proposed only for forest habitats. The loss of key river and riparian habitats was not offset at all and grassland habitats were not restored. Worse still, some additional areas were destroyed during afforestation activities.
Tree planting
Despite the clear requirements in EU Directives, tree planting was only done after the habitats had been destroyed and it will never be able to recreate habitats with similar ecological functions to the destroyed habitats.
Local fish populations
By the end of the project’s construction local fish populations were found to be almost completely extinct throughout several kilometers below the two dams and the weir, and the remaining fish populations above the dams/weir were in a bad state.
Red list species
The Adjaristsqali basin is considered a critical habitat for the Eurasian otter (Lutra lutra), a red list species in Georgia. If the minimum ecological flow in the river is indeed limited to 10% and there are daily changes in the water release from the Shuakhevi powerhouse, the viability of the local otter population would be further threatened.
Bird and bat conservation
The introduction of bird and bat conservation measures have been totally inadequate as they cannot offset the loss of natural, especially riparian, habitats. Two other impacts on bird species are not addressed properly – the migration barrier effect of new powerlines and the impact on the Chorokhi delta because of changed hydrological and sedimentation regime;
Biodiveristy hotspots
The river banks, where traces of wolves, golden jackals, and brown bears have been documented, should be considered a biodiversity hotspot where no effective offsetting is possible.
Gender impact
It is unclear whether the bank and AGL ensured gender equality and proper safeguarding of women as a vulnerable group, and whether or not local women participated in decision-making and were consulted in a culturally appropriate manner.
The project’s impact assessment included no information on gender impact or special provisions for protection of women from local communities, for example in view of influx of workers, no mention of women-headed households or opportunities for women entrepreneurs.
It didn’t present any consideration for the cultural barriers to women’s participation in consultations, in view of the traditional and religious background.
The Land Acquisition and Livelihood Restoration Plan makes a reference to the number of female-headed households, however, it does not analyse the land ownership and land use patterns or the impact on women’s livelihoods if compensation is given to male property owners.
Green Alternative’s 2016 report Gender Impact of Shuakhevi HPP Project And Its Compliance With EBRD Requirements concludes that:
“The Shuakhevi HPP construction has revealed a lot of gender-sensitive problems, on which the project developer failed to respond adequately, as comprehensive social and environmental assessment including gender analysis and assessments has not been conducted at the stage of the project development. […] In addition, there are no evidence that can verify the fact that the project brought sustainable benefits to the affected population and simultaneously strengthened women in Adjara.”
The report recommended that the lenders, in close coordination with the Georgian government, demand from the project developer to draft gender assessment and action plan, and then strictly monitor its implementation – a recommendation that was never followed.
Latest news
IFC Funding for Paravani HPP
Bankwatch in the media | 23 June, 2011European Bank for Reconstruction and Development (EBRD) and International Finance Corporation (IFC) will provide USD 115.5 million credit to finance construction of 87 MW Paravani hydro power plant in the south-west of Georgia.
Read moreBringing Georgian realities to the EBRD drawing board
Blog entry | 30 May, 2011David Chipashvili from Bankwatch member group Green Alternative in Georgia talks about the opportunities and threats in bringing concerns from the ground to the attention of the European Bank for Reconstruction and Development.
Read moreEconomic liberalisation trumps democratisation in EU Neighborhood Policy, says Bankwatch
Press release | 2 March, 2011The strategic review of the European Neighbourhood Policy initiated by the European Commission last year should ensure that funds disbursed through the ENPI mechanism truly promote the development of democratic institutions, human rights and environmental sustainability in Partnership countries, says CEE Bankwatch Network.
Read moreRelated publications
The Upper Horizons complex, Bosnia and Herzegovina
Briefing | 18 December, 2023 | Download PDFThe Upper Horizons hydropower complex has been planned since the mid-20th century, and is planned to consist of three plants — Dabar, Nevesinje and Bileća — linked by a series of tunnels and channels. If completed, it would have a devastating impact on the karst ecosystems of eastern Herzegovina and beyond.
The Ulog hydropower plant on the river Neretva, Bosnia and Herzegovina
Briefing | 18 December, 2023 | Download PDFThe Ulog plant, with a 53-metre high dam, is currently being built on the upper Neretva in the Republika Srpska entity of Bosnia and Herzegovina, in the middle of a nominated candidate Emerald site – an area which should be protected under the Bern Convention.
Joint Statement On the Expansion of the Emerald Network in Countries of the Western Balkans by scientists and representatives of NGOs
Statement | 13 February, 2023 | Download PDFIn early December 2022, 39 scientists and representatives of NGOs from Albania, Austria, Bosnia and Herzegovina, Bulgaria, Croatia, Germany, Greece, Montenegro, North Macedonia, Serbia and Switzerland joined efforts to prepare a shadow list and a map o