Buk Bijela dam and the Upper Drina cascade
Planned as a joint project of public utilities owned by the Republika Srpska entity of Bosnia and Herzegovina and Serbia, Buk Bijela on the upper Drina is being pushed forward in violation of local legislation and international conventions.
Photo: Katja Jemec
Stay informed
We closely follow international public finance and bring critical updates from the ground.
Key facts
- Capacity: 93 MW
- Part of a series of planned hydropower plants on the upper Drina, along with the 44 MW Foča and 43 MW Paunci plants.
- In July 2017, a memorandum on construction of the project was signed with China National Aero-Technology International Engineering Corporation (AVIC-ENG).
- As of early 2022, no financing has been secured.
Key issues
- Hydropower plants on the upper Drina would wreck the key habitat for the Danube Salmon, an endangered fish species
- The environmental permitting processes have been marred with ubiquitous legal violations including a lack of transboundary consultations
- Ongoing legal dispute on whether Republika Srpska needs to obtain state-level consent to issue concessions for the project.
- Lack of information available to the public on the project’s feasibility.
Background
The river Drina is formed by the confluence of the Montenegrin rivers Tara and Piva at the border with Bosnia-Herzegovina. The 93 MW Buk Bijela hydropower plant is planned within Bosnia-Herzegovina, with its reservoir stretching upstream to the Montenegrin border.
Buk Bijela is being pushed by state-owned company Elektroprivreda Republike Srpske (ERS) and a memorandum on construction of the project was signed with China National Aero-Technology International Engineering Corporation (AVIC-ENG) in July 2017. We understand that Chinese state banks may be considering financing for the project, as the European Bank for Reconstruction and Development and the World Bank have both confirmed that they will not finance it.
A larger version of the Buk Bijela project has been disputed since the 1970s due to its impacts on the protected Tara canyon in Montenegro, which is both a UNESCO World Heritage site and part of the Durmitor National Park.
The newer version, while smaller, also suffers from a number of issues inherent to the location of the planned plant. These issues also apply to the Foča and Paunci hydropower plants planned further downstream. A fourth plant, the 44 MW Sutjeska plant, was also planned at some point but has not been mentioned lately.
Drina – the key habitat for the endangered Danube Salmon
The river Drina constitutes the most significant habitat for the endangered Danube Salmon (Hucho hucho) in terms of habitat length. Over the last 100 years Hucho hucho has undergone a massive decline. It is now found only in a few of southeast Europe’s cleanest rivers. This fish is highly sensitive to low oxygen and moderate levels of pollution and is a good indicator for river health. This means that, if the river was in the EU, the stretches of importance for the Danube Salmon, including the upper Drina, would almost certainly be in the Natura 2000 network of protected areas. Moreover, the EU Water Framework Directive virtually forbids projects that degrade the good ecological status of water bodies. So this project would be unlikely to be allowed. In fact, the IUCN assesses that the main current threat to the species is the flow regulation from hydropower dams which impact the species, and their prey, habitat and pollution. Hucho hucho is protected under Annex III of the Bern Convention and Annex II of the European Union Habitats Directive as a species of community interest whose conservation requires the designation of special areas of conservation. This means that, if the river was in the EU, the stretches of importance for the Danube Salmon, including the upper Drina, would almost certainly be in the Natura 2000 network of protected areas and definitely under the EU Water Framework Directive – which virtually forbids projects that degrade the good ecological status of water bodies.
The environmental impact assessment for Buk bijela confirms the presence of Hucho hucho in the Drina. It mentions the construction of fish passes and the fact that these have rarely been implemented in the past for economic reasons, but also that it is uncertain whether they are effective for large fish species like the Danube Salmon. It mentions instead the practice of creating artificial spawning areas. However this seems highly unlikely to be effective for a fish which requires well oxygenated, fast-flowing water and low temperatures.
[There must be] no hydropower development, including micro-hydropower in rivers holding self-sustaining populations of Danube salmon.
Freyhof et al. in the Hucho hucho in the Balkan region report
Legal battles
The upper Drina projects are subject to several ongoing legal cases.
Lack of evidence on the project’s feasibility
The upper Drina area has developed small-scale tourism facilities based on rafting and angling whose activities would be prevented by any nearby dams. Yet no evidence has been published on the economic costs and benefits of the upper Drina projects, nor their financial feasibility.
A World Bank report published in late 2021 identified numerous issues in the design and feasibility assessment for the Buk Bijela and Foča projects, including a relatively high Levelised Cost of Energy (LCOE) for the Buk Bijela plant. It recommended updating the design of the project and updating the feasibility study of the two plants.
Latest news
European Parliament fails to halt disastrous hydropower project jeopardising local livelihoods and endangered species
Press release | 27 September, 2024WWF and CEE Bankwatch Network question the EU Commission’s reasons for putting this decades-old project on the Danube river on its priority investment list.
Read moreActivists say Bosnian dam threatens river life and rafters
Bankwatch in the media | 26 June, 2024KONJIC, Bosnia, June 25 (Reuters) – Environmental activist Lejla Kusturica stood on the banks of Bosnia and Herzegovina’s Neretva river, …
Read moreBattling Rapids and Regulation: Neretva River’s Eco-Warrior Stands Tall
Bankwatch in the media | 25 June, 2024Lejla Kusturica, a Bosnian environmental activist, is concerned about the impact of a new hydro-power dam on the Neretva river’s ecosystem …
Read moreRelated publications
Environmental problems of Shuakhevi Hydro Power Plant, Adjara, Georgia
Briefing | 23 July, 2018 | Download PDFThe 184 MW Shuakhevi Hydro Power Plant is under construction on the Adjaristsqali river and two of its main tributaries in the Autonomous Republic of Adjara, Georgia. The design envisages it as a run-of-the-river plant with capacity of diurnal storage
Nenskra complaint to the European Investment Bank
Official document | 1 June, 2018 | Download PDFIn our opinion, the European Investment Bank (EIB) has failed to comply with the Standard 7 by not respecting the status of Svans as indigenous peoples. The Bank did not fulfill its environmental and social standards: it ignored the project’s significa
Request to the EBRD’s PCM on the Nenskra hydropower project
Official document | 30 May, 2018 | Download PDFThe conclusions of the EBRD’s Environmental and Social Impact Assessment (ESIA) are not guided by detailed field work and focus group research with the affected communities – indigenous Svans, nor are they based on the robust and objective analysis of