Ugljevik III lignite power plant, Bosnia and Herzegovina
The concession for Ugljevik III near Bijeljina in Republika Srpska, Bosnia and Herzegovina, is held by Russian billionaire Rashid Sardarov’s Comsar Energy.
Stay informed
We closely follow international public finance and bring critical updates from the ground.
Background
The original plan was for 2 x 300 MW units which would take lignite from the open cast mines at Delici, Peljave-Tobut, Baljak and part of Ugljevik-Istok. But the capacity has been changed to 700 MW.
Chinese contractors – but no financing
The initial plan was for the plant to be built by the China Power Engineering and Consulting Group Corporation (CPECC). China Development Bank representatives were present at the signing of an agreement between CPECC and the Republika Srpska authorities, indicating that the bank may be interested in financing, however this was never confirmed and media reports indicate that CPECC has dropped out of the project.
A twist occurred in June 2021 when it was reported that China Electric and the Polish-Chinese Sunningwell International Ltd had signed a construction contract for the project, despite the fact these companies had not been previously named as part of the project.
This was expected to result in Chinese financing for the project. However, in September and October 2021 respectively, China pledged to not build new coal-fired power plants abroad at the UN General Assembly and the EU-China Climate Dialogue. In January 2021, in response to a Diplomat article, Sunningwell issued a statement confirming that Chinese loans would not be available for the project.
Despite the project companies putting on a brave face, it is now unclear who could finance the project as China has been the only one willing to back coal in the region in recent years.
A chronology of legal troubles
In July 2017 the project seemed to reach a dead end when the Supreme Court of the Republika Srpska Entity cancelled the environmental permit based on a court challenge by the Center for Environment from Banja Luka.
However, the Ministry of Spatial Planning, Construction and Ecology responded by issuing another permit without repeating the environmental impact assessment process. This second permit was also challenged in court by the Center for Environment, but the process was never concluded because the permit was annulled due to a complaint to the Energy Community.
The complaint was made in December 2014 because the environmental impact assessment was missing key information and the data on likely emissions of SO2, NOx and dust were false.
This led to the Energy Community opening a dispute settlement procedure, which in November 2018 resulted in Bosnia and Herzegovina agreeing not to use the environmental permit, and officially annulling it in June 2019.
However, a new environmental impact assessment was approved at the end of January 2022. It was successfully challenged by the Center for Environment and the court annulled the approval in December 2022 due to deficiencies in the transboundary consultation process. However, the Ministry for Spatial Planning, Construction and Ecology challenged the court’s decision at the Republika Srpska Supreme Court.
Before the court decision, during 2022 the Ministry had also issued a new environmental permit based on the later annulled environmental impact assessment decision. The Center for Environment also challenged this successfully, with the court annulling the permit in July 2023.
Instead of waiting for the Supreme Court’s decision on the environmental assessment, the Ministry re-approved the environmental assessment in early 2023, without repeating the consultation process. Again the Center for Environment challenged the decision in court. After the July court ruling on the environmental permit, the message seemed to have got through, and the Ministry issued a conclusion suspending the permitting process until the Supreme Court makes a decision. But in early October 2023, it changed its mind and issued yet another environmental permit for the project.
Concession shenanigans
In August 2018, local media reported that Comsar was threatening to give up the project unless an extension of the concession from 30 to 45 years was granted, together with a reduction of the capacity from 600 MW to 350 MW, because the plant would otherwise be unprofitable.
In June 2019 it was reported that Republika Srpska’s state-owned electricity company, Elektroprivreda Republike Srpske (ERS), planned to buy off Comsar Energy’s concession for Ugljevik III. The likely cost has been cited at around EUR 90 million. Quite why ERS would buy off the concession rather than the government simply annulling it is far from clear. But in February 2021 it was reported that the concession had been extended from 30 to 45 years instead, despite Comsar not fulfilling its part of the contract.
Latest news
Western Balkan countries invest more than twice as much in coal as in wind power: new Bankwatch analysis
Press release | 26 May, 2016Western Balkan countries are planning investments in wind power, but these are being heavily outweighed by their investments in coal plants, according to a CEE Bankwatch Network analysis launched today. The region’s governments are actively planning 2800 MW of new coal plants but allowing only around 1166 MW of wind power plants to be built.
Read moreThe hefty health toll of coal burning in the Western Balkans – and what is not being done about it
Blog entry | 16 March, 2016While the Energy Community yesterday failed to consider more stringent air pollution rules for the Western Balkans, a new report quantifies the health costs of the region’s coal burning both within the region itself as well as in the neighbouring European Union.
Read moreCSOs deliver over 16 000 signatures for a cleaner energy future in Tirana
Press release | 16 October, 2015Tirana, Albania – A group of CSOs from South East Europe (SEE) delivered over 16 000 petition signatures to Miguel Arias Cañete, EU Commissioner for Energy and Climate Action and Co-Chair of the Ministerial Council of the Energy Community today before its meeting in Tirana, Albania.
Read moreRelated publications
Comply or Close 2024: six years of deadly legal breaches by Western Balkan coal plants
Report | 17 September, 2024 | Download PDFThe end of 2023 marked six years since the deadline passed for power plants in the Western Balkans to meet new air pollution standards. Yet the deadly air pollution from the region’s mostly antiquated coal power plants has hardly decreased at all since 2018.
Western Balkan coal power plants polluted twice as much as those in the EU in 2019
Briefing | 12 July, 2021 | Download PDFThe non-compliance of Western Balkan coal power plants with the emission limits enshrined in the Energy Community Treaty is reflected in the region’s high sulphur dioxide (SO2), nitrogen oxides (NOX) and dust emissions. This briefing looks mainly at th
The great coal jobs fraud (2018 UPDATE)
Study | 28 June, 2018 |This study, an update of our November 2016 analysis, examines the claims and finds that in almost all cases, they are exaggerated. In fact, even the current levels of employment cannot be maintained and some companies such as Elektroprivreda Srbije and