• Skip to primary navigation
  • Skip to main content
  • Skip to footer

Bankwatch

  • About us
    • Our vision
    • Who we are
    • 30 years of Bankwatch
    • Donors & finances
    • Get involved
  • What we do
    • Campaign areas
      • Beyond fossil fuels
      • Rights, democracy and development
      • Finance and biodiversity
      • Funding the energy transformation
      • Cities for People
    • Institutions we monitor
      • European Bank for Reconstruction and Development
      • European Investment Bank
      • Asian Infrastructure Investment Bank
      • Asian Development Bank (ADB)
      • EU funds
    • Our projects
    • Success stories
  • Publications
  • News
    • Blog posts
    • Press releases
    • Stories
    • Podcast
    • Us in the media
    • Videos
  • Русский

Home > Archives for Coal in the Balkans > Sostanj lignite thermal power plant unit 6, Slovenia

Sostanj lignite thermal power plant unit 6, Slovenia

Expert assessment of Alstom’s business ethics

January 4, 2013

The French energy and transport conglomerate Alstom is one of the seven finalists for the People’s Public Eye Awards 2013. This assessment – done by experts from the Institute for Business Ethics of the University of St. Gallen, Switzerland – takes a look at international treaties and Alstom’s conduct in relation to them.


No excuses for the EIB to finance Sostanj

December 21, 2012

Ljubljana — The Slovenian parliament has ratified today – in an extraordinary session, right before the start of the Christmas holidays – the state guarantee contract between the European Investment Bank and the Slovenian government for a 440 million euros loan for the construction of a new coal unit at Sostanj.


EIB energy policy review – Time to lock out climate destructive investments for good

December 14, 2012

The European Investment Bank (EIB), the EU’s bank and also the biggest public financial institution in the world by lending volume, has launched a public consultation on its energy policy and is seeking views from the public and other stakeholders that should feed into a review of one of the EIB’s most crucial lending sectors. The new policy is expected to take effect from June 2013.


Never a dull moment in Slovene power plant soap opera

December 14, 2012

On November 30, the same day as the national government was under fire in the most heated protests Slovenia has seen in years, Slovenia’s ministers of finance and infrastructure added fuel to the flames by signing contracts with Simon Tot, director of the Sostanj lignite power plant for the controversial EUR 1.3 billion Sostanj Unit 6. These contracts prepare the ground for the signing of a state guarantee contract for a EUR 440 million loan from the European Investment Bank (EIB) for the project.


Financial alchemy in Slovenia’s energy sector still results in lignite, not gold

December 11, 2012

Even with the latest investment plan for unit 6 at the Sostanj lignite power plant (TES 6), the project’s economics are (surprise, surprise) still distinctly shaky as an independent analysis shows. Nonetheless, the project looks ever more likely to get a state guarantee from the Slovene government.


Dirty coal gets closer to receiving almost half a billion euros from EU taxpayers

December 3, 2012

The European Investment Bank (EIB) is gearing up to pay 440 million euros to a new 600 MW lignite plant in Slovenia at a time when calls for an end to subsidies for fossil fuels are intensifying all over the world.


That’s what they call sustainable. The EBRD’s 10 billion for sustainable energy

November 6, 2012

The European Bank for Reconstruction and Development boasts of having invested 10 billion euros in sustainable energy since 2006. A closer look reveals that although the bank’s efforts deserve recognition, several investments make a mockery of ‘sustainability’.


Crunch time at Sostanj

November 5, 2012

November is shaping up to be crunch time for a new 600 MW lignite plant planned to be built at Sostanj in Slovenia. If the Slovenian government doesn’t manage to offer a state guarantee for loans from European public banks that should cover half the construction costs by the end of this month, the project could fail. At Bankwatch, we’re preparing our popcorn for the latest Sostanj thriller, on show across Europe this month.


New Slovene legal requirements for Šoštanj lignite power plant (TEŠ 6) regarding CCS

October 17, 2012

On September 8, 2012 new legislation entered into force in Slovenia that requires TEŠ to prepare an assessment of the CCS readiness for its new Unit 6. Pursuant to this legislation, proper assessment of the CCS readiness for the Unit 6 has not taken place yet. As a result, TEŠ has not met the legal requirements regarding the CCS assessment and therefore it is not possible to determine its CCS readiness under the Slovene law. Letter available as pdf: Letter to the European Investment Bank >>> Letter to the European Bank for Reconstruction and Development >>>


Allegations of corruption in Slovenia and across the EU

August 9, 2012

Despite fines and alleged scandals, questionable companies win new contracts every day and posts impressive profits – claims campaign group


« Previous Page
Next Page »

Footer

CEE Bankwatch Network gratefully acknowledges EU funding support.

The content of this website is the sole responsibility of CEE Bankwatch Network and can under no circumstances be regarded as reflecting the position of the European Union.

Unless otherwise noted, the content on this website is licensed under a Creative Commons BY-SA 4.0 License

Your personal data collected on the website is governed by the present Privacy Policy.

Get in touch with us

  • Bluesky
  • Email
  • Facebook
  • Instagram
  • LinkedIn
  • RSS
  • YouTube