Kolubara B lignite-fired power plant, Serbia
The Kolubara B thermal power plant site is situated near Kalenic village, 60 km south-west of Belgrade, at the northern side of the Tamnava Open Cast Mine. The decision to build the 2 x 350 MW plant was taken in 1983 and construction started in 1988. Construction progressed slowly until 1992, when work was suspended due to sanctions against Serbia. At this stage, about 40 per cent of the facility had already been constructed, partly with the assistance of a World Bank loan.
The existing Kolubara A power plant. Power plants within the Kolubara complex already produce more than 50 percent of Serbian electricity.
Stay informed
We closely follow international public finance and bring critical updates from the ground.
Background
Rising from the dead
In 2011 the results of an international tender were announced, in which Italian utility Edison was the only company to submit a bid. Edison’s offer was accepted, and a joint venture agreement signed with Elektroprivreda Srbije on the development of the Kolubara B project in June 2011.
In the meantime, in July 2011 the European Bank for Reconstruction and Development (EBRD) approved an EUR 80 million loan to provide new equipment for the Kolubara lignite mines. For more information about the project see here.
Although in March 2012 the EBRD announced that it was considering investing in the Kolubara B plant, on 6 September 2013, it confirmed to Bankwatch by email that it was no longer examining participation in the project.
For several years, the Kolubara B project appeared to be history. Yet in August 2018, the Minister of Mining and Energy that a working group had been formed to move the project forward. In November 2019, the Minister further announced that a technical study had been completed, which indicated the feasibility of completing the project. In early 2020 a preliminary construction agreement was signed with PowerChina and project-level spatial planning was launched.
Dead again
In May 2021, Serbian media reported that the project had once again been cancelled, this time at the request of the Minister for Energy and Mining.
Long-term problems with corruption at Kolubara
The existing Kolubara mine has frequently been associated with corruption and mismanagement and years of EBRD support for EPS do not seem to have changed this. On 9 September 2013, it was reported that the police had arrested the former director of the Kolubara Mining Basin, Nebojsa Ceran, former financial director Ljubisa Nekic, businessman Radoslav Savatijevic, and several other individuals. The arrestees are suspected of fraud in land expropriation proceedings around the Kolubara mine.
These were not the first cases of corruption in Kolubara. Together with 27 others, in April 2012, Dragan Tomic, former director of the Kolubara coal mine was charged with embezzling USD 11 million from Kolubara between 2006 and 2007. Tomic allegedly paid private companies for unnecessary mining equipment and services. Kolubara was overcharged for the number of hours put in by the private companies, and Kolubara executives did not follow appropriate public procurement procedures. The court hearings started only in 2017 and as of early 2024, appear to still be ongoing. In July 2022 Insajder broadcast a TV show looking at the case and why it is taking so long to conclude.
Latest news
Electricity export ambitions may prove risky for Western Balkans, shows new study
Press release | 19 March, 2015The Western Balkans countries have strong electricity export ambitions that create the danger of stranded assets, finds a new report launched by CEE Bankwatch Network today. If governments take electricity expansion decisions without taking due account of developments in other countries, the region will have to compete with other nearby exporters and may find that its power plants become uneconomic.
Read moreBy the numbers: where will energy come from in the western Balkans?
Blog entry | 19 March, 2015Today we’ve published a new report analysing future energy trends in countries of the western Balkans. From a robust dataset we researched together with the University of Groningen and the consultancy ‘The Advisory House’, we’ve pulled out a couple of illustrations.
Read moreEnergy Community countries so rich they can afford to eschew climate action?
Blog entry | 11 March, 2015Planned new coal capacities will result in high additional costs for Energy Community countries. Transforming their energy sectors into efficient, sustainable renewables-based systems is not only possible but a cost-effective way forward.
Read moreRelated publications
Comply or Close 2024: six years of deadly legal breaches by Western Balkan coal plants
Report | 17 September, 2024 | Download PDFThe end of 2023 marked six years since the deadline passed for power plants in the Western Balkans to meet new air pollution standards. Yet the deadly air pollution from the region’s mostly antiquated coal power plants has hardly decreased at all since 2018.
Western Balkan coal power plants polluted twice as much as those in the EU in 2019
Briefing | 12 July, 2021 | Download PDFThe non-compliance of Western Balkan coal power plants with the emission limits enshrined in the Energy Community Treaty is reflected in the region’s high sulphur dioxide (SO2), nitrogen oxides (NOX) and dust emissions. This briefing looks mainly at th
The great coal jobs fraud (2018 UPDATE)
Study | 28 June, 2018 |This study, an update of our November 2016 analysis, examines the claims and finds that in almost all cases, they are exaggerated. In fact, even the current levels of employment cannot be maintained and some companies such as Elektroprivreda Srbije and