A 35 MW hydropower plant is currently under construction on a pristine section of the Neretva river at Ulog. Seven more plants are also planned further upstream.
Stay informed
We closely follow international public finance and bring critical updates from the ground.
Key facts
Project promoter: EFT – HE Ulog d.o.o, a subsidiary of the EFT Group (Ulog) and MHE Marvel d.o.o. (HES Gornja Neretva)
Installed capacity: 35 MW
Lead contractor: Sinohydro, China
Financing: Ulog: Reportedly, EFT’s own funds; No information available for Marvel’s plants.
River: Upper Neretva
Protected areas: Gornji tok Neretve Emerald Site
Other key risks: Geological – landslides
Key issues
– The Ulog project is being built and seven more plants are planned in an Emerald site.
– The terrain appears unstable – two workers were killed by landslides in 2013.
– People downstream in Konjic fear that earthquakes could cause flooding.
Background
The EFT Group’s 35 MW Ulog plant, with a 53-metre high dam, is currently being built by China’s Sinohydro. A series of seven smaller plants is also planned further upstream by local company Marvel d.o.o. and would turn most of the upper course of the river – a section of about 38 kilometres – into a series of dams, pipes and reservoirs.
Risky construction
Work on the Ulog plant started for the first time in 2013, but in July that year, two fatal incidents took place and works stopped. On 4 July, a worker from the Prijedorputevi company was killed by a rock breaking off a cliff face while building access roads. Only four days later on 8 July, another worker from the same company was also killed by a rockslide, and another worker taken to hospital. After this, the works were put on hold while more research was done, but in 2017 the project was redesigned with the dam slightly further downstream. It remains to be seen whether the new design will be any safer.
People living downstream fear that the operational phase of the plant will also put them in danger, as the location where the plant is being built is where a landslide in 1934 caused the biggest floods in the history of Konjic. According to local people, the landslide blocked the Neretva, which then burst through, sending a massive wave downstream.
Neretva - one of the most biodiverse rivers in Europe
The projects are also subject to international legal challenges under the Bern Convention and Energy Community Treaty, as the Bosnia and Herzegovina authorities failed to protect the upper Neretva – part of the Convention’s Emerald Network – by permitting hydropower development along its entire length.
Although the environmental impact assessment studies for the Ulog project and the other Upper Neretva hydropower projects identified several significant species such as otters and crayfish being present, the government of the Republika Srpska Entity concluded, without any evidence, that these projects would not have a negative impact on the environment and could be implemented.
In July 2022, the first Neretva Science Week, organised by the Center for Environment together with Riverwatch and Euronatur, identified 1300 species living on the upper Neretva, of which 24 were new for Bosnia and Herzegovina, and eight species were new to science.
High-risk investments
It is not clear whether the Ulog plant will be used for peak electricity generation and if so, what the downstream impacts of major daily variations in water level will be. Considering the rich biodiversity downstream above Konjic, including marble trout, the endangered soft-mouthed trout, white-clawed crayfish, kingfishers and endemic invertebrates, this is a major concern.
Despite being under construction, the Ulog project remains very high-risk and public opposition, particularly from the downstream Federation of Bosnia and Herzegovina, is increasing. As of June 2023, the other seven plants are not moving ahead significantly.
Latest news
Victory for civil society as EBRD cancels loan for controversial Croatian dam
Press release | 28 May, 2013Zagreb, May 28 – Croatian electricity company HEP and the European Bank for Reconstruction and Development (EBRD) have cancelled a EUR 123 million loan contract for the controversial Ombla underground hydropower plant near Dubrovnik, HEP has announced yesterday. The EBRD financing would have covered the biggest bulk of the EUR 152.4 million estimated to be needed for construction.
Read more[Campaign update] EBRD still not withdrawing from damaging Ombla hydropower project, NGOs call on bank to heed new evidence
Blog entry | 13 May, 2013Despite having a slew of good reasons not to support the damaging Ombla hydropower plan in Croatia, the European Bank for Reconstruction and Development still didn’t confirm during recent meetings that it would withdraw from the project.
Read moreGuest post: New studies fail to prove that the Ombla hydroplant is fit for EBRD financing
Blog entry | 22 April, 2013The EBRD’s involvement in the Ombla hydropower plant project has from the start been a story of insufficient scrutiny and cutting procedural corners, followed by an attempt to patch things up by commissioning a belated nature impact assessment. The assessment highlights the Ombla area’s natural importance and captures some of the harm that would be done by the dam, but fails to draw the right conclusions, says Jagoda Munic, President of Friends of the Earth International and Biodiversity Programme Co-ordinator at Zelena akcija/Friends of the Earth Croatia.
Read moreRelated publications
The Upper Horizons complex, Bosnia and Herzegovina
Briefing | 18 December, 2023 | Download PDFThe Upper Horizons hydropower complex has been planned since the mid-20th century, and is planned to consist of three plants — Dabar, Nevesinje and Bileća — linked by a series of tunnels and channels. If completed, it would have a devastating impact on the karst ecosystems of eastern Herzegovina and beyond.
The Ulog hydropower plant on the river Neretva, Bosnia and Herzegovina
Briefing | 18 December, 2023 | Download PDFThe Ulog plant, with a 53-metre high dam, is currently being built on the upper Neretva in the Republika Srpska entity of Bosnia and Herzegovina, in the middle of a nominated candidate Emerald site – an area which should be protected under the Bern Convention.
Joint Statement On the Expansion of the Emerald Network in Countries of the Western Balkans by scientists and representatives of NGOs
Statement | 13 February, 2023 | Download PDFIn early December 2022, 39 scientists and representatives of NGOs from Albania, Austria, Bosnia and Herzegovina, Bulgaria, Croatia, Germany, Greece, Montenegro, North Macedonia, Serbia and Switzerland joined efforts to prepare a shadow list and a map o