Kosova e Re lignite power plant, Kosovo
CANCELLED: For more than a decade, successive Kosovo governments planned to build a new 500 MW lignite plant (around 450 MW net), Kosova e Re or New Kosovo. The controversial project was finally cancelled in 2020 after concession-holder ContourGlobal pulled out.
The Kosovo A power plant near Prishtina. Image by Andreas Welch, CC BY-NC-SA
Stay informed
We closely follow international public finance and bring critical updates from the ground.
Background
For more than a decade, successive Kosovo governments planned to build a new 500 MW lignite plant (around 450 MW net), Kosova e Re or New Kosovo.
In fact, the plans started out as a planned 2000 MW facility which, it was hoped, would turn the country into a leading energy exporter for the Balkans. Yet, lack of investors, lack of demand, and resistance to a massive lignite project gradually diminished ambitions.
One step forward, two steps back
In December 2017, the Kosovo government signed a series of contracts with UK-registered ContourGlobal for a 20-year concession to build and operate a plant with a net capacity of around 450 MW.
Yet just as the project seemed to be taking a significant step forward, its long-time backer, the World Bank, was getting cold feet. In October 2018, the Bank’s President Kim ended years of speculation by confirming that the Bank had dropped the project because its assessment had shown that it was no longer the least-cost option for Kosovo. Around a month later, the EBRD also confirmed it would not support the project.
ContourGlobal’s CEO then claimed that financing was expected from the US Overseas Private Investment Corporation (OPIC) – now renamed as the U.S. International Development Finance Corporation (DFC) – and various export credit agencies. However, financing was never approved for the project.
Illegal power purchase agreement and massive costs for consumers and the State
The power purchase contract was almost certainly illegal under the Energy Community Treaty because it would have resulted in the transfer of almost all risks from the investor to the State.
The Energy Community Secretariat had repeatedly warned the Kosovar government about this, but seeing no inclination on the Government’s side to cancel the contract, in May 2019 a group of NGOs filed an official complaint to the Energy Community.
In December 2019 the Secretariat opened a case against Kosovo, stating that certain measures, such as guaranteed energy purchase and availability payments over 20 years, the sale of the plant site below market value, and several other measures constitute State aid. In addition, the measures had not been notified to the competent State aid authority and are therefore automatically illegal.
The Kosovar state obliged itself to buy the plant’s electricity, thus giving itself no incentive to develop renewable options. It also committed to pay an availability fee, just for having the plant in an operational state even when it was not operating.
Sound familiar? This is the same mechanism used for public-private partnership projects in non-profit sectors such as hospitals and schools that has been widely criticised for poor value for money.
Concerns about costs were heightened by the Kosova e Re project only receiving a single bid, which meant there was never any real chance of getting good value for money. The internal rate of return was reduced from 27 percent to 18.5 percent, but this was still very high indeed.
For all these reasons, the Kosovo parliament never ratified the commercial contracts and the project was left hanging for several years.
Illegal environmental impact assessment process
Poor quality environmental impact assessments (EIAs) are unfortunately common in the Balkans, but approving an EIA for a 500 MW coal plant without any public consultation taking place is still quite exceptional.
The news slipped out during a Parliament session in January 2019 and when BIRN Kosovo followed up with the Government, it was confirmed that the environmental impact assessment had been approved in December 2018. Kosovar NGOs therefore initiated a lawsuit against the Government and submitted a complaint to the Energy Community regarding violations of the EU EIA Directive.
An end to the agony
In March 2020, ContourGlobal finally announced its exit from the project. The company stated that would now impossible for the project to meet the required milestones, citing, among other things, the fact that the new government in Kosovo had publicly opposed the contract.
Latest news
Western Balkan countries invest more than twice as much in coal as in wind power: new Bankwatch analysis
Press release | 26 May, 2016Western Balkan countries are planning investments in wind power, but these are being heavily outweighed by their investments in coal plants, according to a CEE Bankwatch Network analysis launched today. The region’s governments are actively planning 2800 MW of new coal plants but allowing only around 1166 MW of wind power plants to be built.
Read moreThe hefty health toll of coal burning in the Western Balkans – and what is not being done about it
Blog entry | 16 March, 2016While the Energy Community yesterday failed to consider more stringent air pollution rules for the Western Balkans, a new report quantifies the health costs of the region’s coal burning both within the region itself as well as in the neighbouring European Union.
Read moreGuest post: New report shows that New Kosovo Power Plant would worsen poverty and cripple a fragile economy
Blog entry | 12 January, 2016No-one will ‘freeze to death’ if the planned lignite-fired power plant in Kosovo does not receive support from multilateral development banks, but if it does, low-income households may well end up choosing between electricity and food. How can an institution, whose very mission is to end poverty, justify this project?
Read moreRelated publications
Comply or Close 2024: six years of deadly legal breaches by Western Balkan coal plants
Report | 17 September, 2024 | Download PDFThe end of 2023 marked six years since the deadline passed for power plants in the Western Balkans to meet new air pollution standards. Yet the deadly air pollution from the region’s mostly antiquated coal power plants has hardly decreased at all since 2018.
Western Balkan coal power plants polluted twice as much as those in the EU in 2019
Briefing | 12 July, 2021 | Download PDFThe non-compliance of Western Balkan coal power plants with the emission limits enshrined in the Energy Community Treaty is reflected in the region’s high sulphur dioxide (SO2), nitrogen oxides (NOX) and dust emissions. This briefing looks mainly at th
The great coal jobs fraud (2018 UPDATE)
Study | 28 June, 2018 |This study, an update of our November 2016 analysis, examines the claims and finds that in almost all cases, they are exaggerated. In fact, even the current levels of employment cannot be maintained and some companies such as Elektroprivreda Srbije and